 |
In
1888, with the threat
of a lawsuit because of unsafe working conditions
in the old Court House, Oxford County Council appointed
a special committee
to identify the requirements for a new Court House. As
well, the committee was to investigate other Court Houses.
That fall, the committee reported that the Council should
advertise
for a new Court House that would "be as fire proof
as possible" and would cost no more than $75,000.00
"complete and furnished."
|
|
The response
to this competition was amazing, with queries from over eighty
architects and denouncements
from the Architectural Guild of Toronto that no suitable edifice
could be built for that sum. Eventually though, architectural
plans were submitted by sixteen architectural firms, with the
contract
being awarded to James
Balfour of Hamilton. Since
the Council had changed its mind about the project and was
now stipulating that the architect was to also superintend
construction of the project for a fee of 4% of the contract,
Balfour then withdrew
his plans. In his correspondence, he stated "... that
his building could not be erected in a substantial manner
for the sum mentioned in your instructions." With that,
the top prize
was awarded to Robert
Thomas Brookes, an architect from Detroit. Brookes immediately
set up specifications
for tenders for construction, with the lowest
bidders being William
C. Smith and Company of Detroit.
Originally,
the plan had been to build the new court house behind the
older one, so that the offices and chambers could still be
used, but County Council reneged on that decision, deciding
instead to allow the construction on the best building site.
Arrangements were made to set up the Clerk's Office and a
temporary Council Chamber in vacant space over White
and White's Drug Store in downtown Woodstock, while the
Sheriff worked in a small building on his Vansittart Avenue
property. The courts were set up in the ballroom on the second
floor of the Woodstock Town Hall.
Following
the demolition
of the old building in early 1890, construction began on the
new Court House. As the building progressed, the reliability
and competence
of both the architect and the contractor came into question.
Independent inspections
by two consulting firms in the summer of 1890 confirmed that
the work was not being carried out satisfactorily and that
the foundation walls would not be able to support the finished
building. In August, Robert Brookes was dismissed
and a new architectural firm was hired in December. The new
architects, Cuthbertson and Fowler, recommended that the basement
walls were "most unsatisfactory, unworkmanlike and
unsafe" and that they should be taken down and rebuilt.
As a result, the first contractors were dismissed
over conflicts regarding the extra work involved. A contract
for completion
of the Court House was awarded to a Toronto builder, A.J.
Brown, in June 1891. Tenders
were called for mechanical systems and interior furnishings,
with most of the office
furniture being provided by The
Canadian Office and School Furniture Company.
Said to
be one of the finest
County buildings in the province, the County of Oxford
Court House building was formally dedicated
in December 1892, with a grand
ball held in the Superior Court Room on the top floor,
the following February. Including costs for the building,
furnishings, exterior landscaping and interest, the total
cost of the Court House was $125,086.00.
Copyright ©
2002 County of Oxford Archives. All Rights Reserved.
|
 |